Village Core:
The Village Garage is moving along quickly with the final concrete pours occurring in the next two weeks. We have all the walls poured with the exception of the 42” cash walls on the upper level. Utility work is progressing as well with water and sewer wrapping up this week and shallow utilities being installed over the next two weeks. Construction of the new bridge will begin in the next two weeks as well and coordination has been completed to install the garage gates by mid-October. The design for the village signage has been revised and final coordination for installation is proceeding this week. Completion of the garage is on schedule for mid-November. Foundations for the commercial and residential buildings on the west side of the village will begin in October and final road paving and utilities will completed in early November.
Fraser Crossing and Founders Pointe:
Construction on Fraser and Founders continues to move onward and even outward. The ski area is closed for the summer which also allows construction crews a little more to room to perform site work. Including the demolition of the existing parking hut that was located in the center of Winter Park Drive which will be replaced yet this fall with a new parking hut that will be located in a similar location further south.
Fraser Crossing's finishes are now really shaping up nicely. The first load of trees arrives around September 20th and the first plantings to take place will start on the Amenity deck. We are now nearly completed with flooring in the homes from floors three through six which now allows us to start the painting of common areas which will then be followed by flooring in these areas shortly thereafter. Installation of furniture, fixtures and equipment on Fraser is scheduled to begin the first week of October.
Now that drywall has been substantially completed in Fraser the contractor has moved those crews to Founder’s to essentially double the crews in that building. There is a tremendous amount of activity on every floor in Founder’s including completion of the roof, mechanical, and electrical systems. As soon as dry wall is complete on levels three to six in the next two weeks, trim and finishes will begin on those levels while drywall in completed on the first tow floors.
To say that there is a lot going on is an understatement.
-Kevin Haupt, Construction Manager